Productivity rate in concrete plastering of interior brick wall
View/ Open
Date
2020-01-27Author
Suksoom, Paisarn
Monkaew, Sunun
ไพศาล สุขสม
สุนันท์ มนต์แก้ว
Metadata
Show full item recordAbstract
The purpose of this research was to study productivity rate in concrete plastering of interior brick wall by studying 2 construction projects in Bangkok. The researcher divided the methods of labor productivity into two categories: (1) direct labor production technique and (2) field rating technique. The direct labor productivity technique of project A is about 1.38 m2/person/hr. and project B is about 1.19 m2/person/hr. by field rating technique project A had 77.75 % of workers in work status, project B had 73.75% of workers in work status. The error rate was 4.08 % and 4.31 % respectively, at the 95% confidence level.
Project A has higher productivity rate than project B because project manager A chooses ready-mixed plaster for plastering. Project B selects cement mix (silica cement) mixed with fine sand cement mixer and water, which take longer to prepare than Project A, resulted cost of materials increase for 28.21 %.Meanwhile, the working time for wall plastering could take longer for 13.77 %. It can be concluded that the selection of material for work is another factor affecting labor productivity
Collections
- Research Report [5]